Situated in Burnley, Lancashire

B&E Boys completed the £4 million BREEAM Excellent Scheme for Burnley College

This was a negotiated project from a Two Stage Tender process and the brief involved constructing two steel framed blocks within a design & build framework. The works were for the construction and completion of a new steel framed Construction Skills Centre, the remediation and capping of two former gas holders and the construction of a new Technology Block with external paved areas.

The works were carried out adjacent to the busy campus and in particular having handed over the first block early, personnel and traffic had to be carefully managed with good signage, introduction of traffic and personnel barriers, careful deliveries and communication with adjacent building users wherever possible.

B&E Boys and the College worked well together to overcome any issues with teaching and exam timetables.