Situated in Bury, Lancashire

To create a concrete channel and generator house alongside the River Roche to accommodate a 75kw hydro electric turbine.

Works included re-grading of the river bed, installation of cofferdams and temporary support works to enable excavation of a 5m wide channel to a depth of 6m, of which 2m were below the water level. Techniques were employed to enable over 100 cubic metres of concrete to be cast along side a river, creating a new water channel, co-ordinating the lifting of an Archimedes screw into position and then finally grouting into position.

J2 Business Park situated near B&Q Warehouse, Bury on the M66 is home to The Bury Black Pudding Co. Ltd who will utilise much of the electricity generated.

The original water workings date back to 1766 and a date stone has been retained in original position as part of the new installation.