Situated in Middleton, Greater Manchester.

This project comprised of three phases which overcame many logistics and access challenges and was delivered over 32 weeks. Phase 1 consisted of an extension to the existing school building, drainage, mechanical and electrical installations, alongside various external works. Phase 2 included alterations to the existing accommodation and associated installations. Finally, Phase 3 featured internal modifications. In keeping with the school’s community ethos, parents were kept fully informed at all stages of the project.

In all, the alterations, demolitions and refurbishment affected approximately 75% of the existing school accommodation. Substantial mechanical, electrical and data works throughout the building included a new electric and gas mains supply being installed. A new school entrance, inclusive of external steps, ramps and a disabled lift, was constructed, alongside offices and toilets and two new classrooms, to facilitate an extra 21 pupils being added to the school roll.